The budget for production automation: how to set it without knowing the price of the solution

In this article I want to walk through the whole process of costing an investment in production automation, in order to answer one of the most important — and most emotive — questions: what budget do we have? I reverse the usual order of the calculation and start by defining the situation in your plant today — which lets you decide on the basis of facts rather than theory.

Contents How to set an automation budget – before you start collecting quotes
Contents

In this article you will learn:

  1. How to set your production automation budget before you start collecting quotes – without knowing the price of the solution
  2. Why ROI cannot be the starting point of the conversation, and what the COI indicator is — the one that describes your situation today
  3. What a production operator really costs in 2026 and how to calculate the total cost of the machine that replaces them
  4. Why 2020–2025 is a turning point for industrial production in Poland and how it affects small and medium-sized companies
  5. When automation definitely makes sense and when it is better to wait or look at a different process – real examples and calculations

How to set an automation budget – before you start collecting quotes

Automating a production process should rest on numbers, and the budget should follow from the cost you already carry or will carry in the future (in the case of a new project or hiring another person). In practice, when investment comes up, what I usually meet is a situation where an idea has appeared, or at least a feeling that something needs to change and improve, but there is no information on which to base that decision consciously — which usually reduces the whole discussion to one question: how much will such a station cost? Only once some quote appears do the first conversations and analyses begin. The moment for a decision arrives, questions are asked whether we can spend that much and whether it will pay off — and I often wonder what goes into the calculation at that stage and on what data the decision is based. This approach creates a series of misunderstandings between supplier and client, stretches out the time needed to prepare a quote, makes it harder to match the optimal solution to the specific situation of a given plant, and often takes up the time of both sides unnecessarily. That is why in this article I go through the whole process comprehensively and try to justify why the approach needs to change.

In what follows I will try to explain why I believe the most commonly used return on investment indicator (ROI) is used wrongly — too early in the buying process — and what happened in Poland between 2020 and 2025 that so drastically changed the situation of manufacturing companies.

The pay calculations you will find in this article are based on reports and official publications from GUS; the sick leave data comes from a ZUS report. The wage trend was derived from data on average pay in Poland between 2005 and 2025.

Before I start, a few terms need explaining, because most of the differences come precisely from both sides counting different things. These are indicators I have selected; they do not exhaust the subject – many more are in use – but I take the ones that have the greatest influence on the calculations.

Legend

CAPEX
Capital outlay on a new fixed asset or an increase in its value – the machine, transport, production start-up – usually included in the supplier's quote, plus what you add on your side (preparing the floor, electrical and pneumatic installation and so on).
OPEX
The running cost of operating the station: energy, wear parts, residual operator attendance, repairs outside the warranty.
TCOTotal Cost of Ownership
Put simply: CAPEX + OPEX over the entire period of use.
ROIReturn on Investment
Return on investment. It answers the question of whether this particular quote stands up — it requires knowing the price of the solution and the time horizon.
COICost of Inaction
Cost of inaction. It describes your situation today, with no investment at all — how much you will pay to keep the current process unchanged over the coming years.
Total cost to the employer
Gross pay + employer contributions, training, workwear, medical check-ups, recruitment and HR costs, supervision costs (team leaders) and others.
SSFShift Staffing Factor
Station staffing factor. It states how many people I have to employ to keep one person continuously present at a workstation, allowing for: sick leave, holidays, training and medical check-ups.
SCFShift Cost Factor
Shift cost factor. It states how much higher the total cost of employing a worker is in a multi-shift system (2- or 3-shift) compared with day shift only.
Wage indexation
Average annual rate of wage growth

To answer the question of what budget we have, we will need:

  1. The definitions from the legend above, which form the basis for the calculations further on
  2. A time horizon
  3. Data on production in your plant:
    • 1/2/3-shift operation
    • current throughput, how many people work and for how long to cover current and future demand

Why ROI cannot be the starting point of a conversation about automation and what the COI indicator is that defines your situation today

The most common mistake I see in conversations about investing in automation is using the return on investment indicator, ROI, which requires knowing the price of the solution — and that is the last thing you learn in the buying process.

The formula used here looks as follows:

ROI= Net profitCost of the investment × 100%

Example:

  1. Cost of the investment: 100 000 PLN
  2. Revenue from the investment: 130 000 PLN
  3. Net profit: 30 000 PLN
  4. ROI = 30 000 / 100 000 × 100% = 30%

As you can see, calculating ROI requires the cost of the investment to be known – you can only work this indicator out once you have a quote, which is why most companies push for an offer from the start: how much will it cost? That reduces the entire conversation to price. The lower the price, the higher the ROI – is that really so? I check this on concrete examples in section 5.

Why does this matter so much? Production operators are paid differently, companies are at different stages of development and in different financial situations, and boards disagree on what the payback period should be. Let us look at an example:

Example 1: A station palletising cartons of finished product

DESCRIPTIONINVESTOR 1INVESTOR 2
Required payback periodwithin a yearwithin 3 years
Working pattern1 shift3 shifts
Market situationsales stable, orders growing slightlynew product, production planned for 5 years, orders growing steadily
Staffing consequencesheadcount unchangedanother person has to be hired
Budget for the same processapprox. 150 000 PLNapprox. 1 700 000 PLN

Automating exactly the same process, two different companies, and a budget difference of 150 thousand against 1.7 million. What is a supplier supposed to quote without knowing these facts? The priorities will be completely different, and so will the expectations.

I will come to the figures in the table above in the next section, where I calculate them on a concrete model.

In the first case automation does not make sense yet; some simple, inexpensive improvements to packing are probably worth introducing. It is worth returning to the analysis once a full second shift has to be started and a good financial position encourages the investor to extend the required payback period to 2 years.

In the second case the cheapest offer, based on lower-quality components, a shorter warranty, lower energy efficiency or lower throughput, will ultimately deliver a lower ROI. The question is whether the investor took that into account at the moment of deciding.

Compare it with the decision to buy a car – what do we usually take into account:

  • the purchase price (CAPEX)
  • average fuel consumption (OPEX)
  • reliability, the cost of spare and wear parts (OPEX)

and much more.

If I have a budget of 50 thousand PLN and cover an average of 5 thousand km a year, I am looking for a different car than if I had 150 thousand PLN and covered 25 thousand km a year.

For that reason I believe a conversation about investment should start with an analysis of the situation in your plant and be based on concrete figures rather than guesses – before the first contact with a supplier. If you do not know how to go about it but would like to check whether such an investment could make sense for you, get in touch with us. In a short, free phone call we will establish whether there is real potential for automation, or whether it is better to wait or look at a different process.

Coming back to setting the budget – the COI indicator comes to our aid, and the conversation about automation should start with it. COI answers the question of how much this process costs me today with no investment at all, and how much leaving it unchanged will cost me over the coming years. For any investor, business owner or decision-maker on a corporate board that information is crucial, and it allows a prospective supplier to select a solution matched to the expectations, the time horizon and the financial means.

What a production operator really costs in 2026

One production worker, assuming 1-shift operation, costs an employer in Poland 121 986 PLN a year, that is 10 165 PLN a month — calculated on the basis of median gross pay of 7 690.82 PLN GUS, Feb 2026.

Here, however, the first discrepancy appears – the cost of an operator is not the same as the cost of a staffed station – and at this point I return to calculating the first indicator from the table of terms:

Station staffing factor (SSF)

One full-time post does not fill the nominal working time of one station, and this is an aspect that is often overlooked.

I derive the SSF from actual data. Nominal working time in 2026 is 251 working days (excluding public holidays and weekends) of 8 hours. I apply the following deductions:

  • holiday 26 days
  • sick leave: 12 days, reduced against the average in ZUS data (14.65 days)
  • training/medical check-ups 2 days
  • other absences (compassionate and carer's leave) 2 days

In the calculation for 1-shift operation I assume sick leave of 12 days on average. In companies of more than 1000 people and on 3-shift operation these values are correspondingly higher, and that is accounted for by applying the additional SCF factor.

SSF = 251 / 209 = 1.2
  1. 251 – 26 – 12 – 2 – 2 = 209 days
  1. SSF1 = 1.2 for 1-shift operation
  2. SSF2 = 2.4 for 2-shift operation
  3. SSF3 = 3.6 for 3-shift operation

Shift cost factor SCF (Shift Cost Factor)

This is my own multiplier, allowing a more precise calculation that accounts for the additional costs of running a second and third shift. The reference point is concrete data:

Looking at the size of the entity, the highest median pay was recorded, as in previous periods, in entities employing 1000 people and more — 9 146.18 PLN (118.9% of the overall figure), and the lowest in entities employing 9 people or fewer — at the minimum wage level, that is 4 806.00 PLN (62.5% of the overall figure)

GUS

It is in companies of more than 1000 people that we most often find 3-shift operation and higher total pay, which follows from statutory night-work and shift allowances. On top of that, higher turnover and the associated recruitment costs, as well as longer sickness absence, have to be taken into account.

So I assume the following:

Total cost to the employer for one operator

ITEMFORMULA / RATEPLN / YEAR
Gross pay GUS12 × 7 690.82 PLN92 289.84
ZUS, Labour Fund, FGŚP20.48% × 92 289.8418 900.96
PPK on the employer's side1.5% × 92 289.841 384.35
Indirect costs ASSUMPTION medical cover, insurance, workwear, health and safety and medical check-ups, training, transport, meals400 PLN × 124 800.00
ZFŚS (mandatory above 50 people)annual provision2 943.00
Recruitment and turnover ASSUMPTION 5% turnover × 30% of 111 190.80 PLN (pay + ZUS, Labour Fund, FGŚP) = 1.5%1.5% × 111 190.801 667.86
TOTAL121 986

The cost of staffing a station

WORKING PATTERNSSFSCFPLN / YEARPLN / MONTH
1 shift1.201.00146 38312 199
2 shifts2.401.08316 18726 349
3 shifts3.601.19522 58843 549
Annual cost of staffing one production station
Annual cost of staffing one production stationPLN / year: 146, 316, 5230 k200 k400 k600 k1 shift: 146 k PLN146 k PLN1 shiftSSF 1.20 × SCF 1.002 shifts: 316 k PLN316 k PLN2 shiftsSSF 2.40 × SCF 1.083 shifts: 523 k PLN523 k PLN3 shiftsSSF 3.60 × SCF 1.19PLN / year
Annual cost of staffing one production stationPLN / year: 146, 316, 5230 k200 k400 k600 kPLN / year1 shiftSSF 1.20 × SCF1.00146 k PLN2 shiftsSSF 2.40 × SCF1.08316 k PLN3 shiftsSSF 3.60 × SCF1.19523 k PLN
Annual cost of staffing one production station
1 shift2 shifts3 shifts
PLN / year146 k PLN316 k PLN523 k PLN

COI — what it costs to keep the process unchanged

For a station running three shifts the cost of inaction is 1.07 million PLN over 24 months, 1.65 million over 36 and 2.89 million over 60 months — with a conservative indexation of 5% a year. You carry this cost whether or not you decide to automate.

Why 5% is conservative I explain in section 4. Average pay in the national economy grew by 11.5% a year between 2020 and 2025 GUS.

COI — the accumulating cost of inactionwage indexation 5% a year
  • 1 shift
  • 2 shifts
  • 3 shifts
COI — the accumulating cost of inaction1 shift: 0,15, 0,3, 0,46, 0,63, 0,81. 2 shifts: 0,32, 0,65, 1, 1,36, 1,75. 3 shifts: 0,52, 1,07, 1,65, 2,25, 2,890 m0,5 m1 m1,5 m2 m2,5 m3 m122436486012 · 1 shift: 0,15 m24 · 1 shift: 0,3 m36 · 1 shift: 0,46 m48 · 1 shift: 0,63 m60 · 1 shift: 0,81 m0,81 m12 · 2 shifts: 0,32 m24 · 2 shifts: 0,65 m36 · 2 shifts: 1 m48 · 2 shifts: 1,36 m60 · 2 shifts: 1,75 m1,75 m12 · 3 shifts: 0,52 m24 · 3 shifts: 1,07 m36 · 3 shifts: 1,65 m48 · 3 shifts: 2,25 m60 · 3 shifts: 2,89 m2,89 mPLN, cumulativemonths of keeping the process unchanged
COI — the accumulating cost of inaction1 shift: 0,15, 0,3, 0,46, 0,63, 0,81. 2 shifts: 0,32, 0,65, 1, 1,36, 1,75. 3 shifts: 0,52, 1,07, 1,65, 2,25, 2,890 m1 m2 m3 m122436486012 · 1 shift: 0,15 m24 · 1 shift: 0,3 m36 · 1 shift: 0,46 m48 · 1 shift: 0,63 m60 · 1 shift: 0,81 m0,81 m12 · 2 shifts: 0,32 m24 · 2 shifts: 0,65 m36 · 2 shifts: 1 m48 · 2 shifts: 1,36 m60 · 2 shifts: 1,75 m1,75 m12 · 3 shifts: 0,52 m24 · 3 shifts: 1,07 m36 · 3 shifts: 1,65 m48 · 3 shifts: 2,25 m60 · 3 shifts: 2,89 m2,89 mPLN, cumulativemonths of keeping the process unchanged
COI — the accumulating cost of inaction
1224364860
1 shift0,15 m0,3 m0,46 m0,63 m0,81 m
2 shifts0,32 m0,65 m1 m1,36 m1,75 m
3 shifts0,52 m1,07 m1,65 m2,25 m2,89 m
WORKING PATTERN12 MTHS24 MTHS36 MTHS48 MTHS60 MTHS
1 shift146 383300 086461 473630 930808 860
2 shifts316 188648 185996 7821 362 8091 747 137
3 shifts522 5881 071 3061 647 4592 252 4202 887 629

How to calculate the total cost of the machine that replaces an operator

The subject has to be approached honestly and stated plainly: an automated station also generates additional costs. OPEX has to be subtracted from COI to arrive at the budget — in practice, working out the fixed costs after automation means accounting for:

  • Energy: for example 3 kW of average draw (compressed air compressor supply + robot supply) × 2 008 h × the number of shifts × 1.2 PLN/kWh ASSUMPTION — from 7.2 thousand PLN on one shift to 21.7 thousand on three.
  • Service, spare parts and wear parts: 3% of the outlay per year ASSUMPTION.
  • Residual operator attendance: it depends on the autonomy achieved and on how much involvement is needed; for example, in one of our projects the operator comes to the station after automation usually for 10 minutes once every 4 hours — they top up components and collect the finished product. That is time which has to be subtracted in the calculations.

CAPEX + OPEX over the entire period of use is TCO — and it is TCO, not the price in the quote, that should be compared with COI. Breakdowns and downtime are the hardest item to estimate in this account. Some machines, particularly the most complex ones, do not reach full throughput in the first weeks of operation, often because setting them up optimally requires steady series production, properly trained operators and dimensional stability of the components. That is why in practice, where the technology and the budget allow, stations are designed with a throughput margin that covers those differences.

BUDGET – the result of the whole calculation

An example for a robotic station fitted with 10 additional pneumatic actuators.

The budget is COI over a given time horizon less the station's OPEX over the same period.

WORKING PATTERNITEM12 MTHS24 MTHS36 MTHS48 MTHS60 MTHS
1 shiftCOI146 383300 086461 473630 930808 860
OPEX17 20342 42175 639116 889166 240
BUDGET129 180257 665385 834514 041642 620
2 shiftsCOI316 188648 185996 7821 362 8091 747 137
OPEX36 03789 447160 198248 349354 049
BUDGET280 151558 738836 5841 114 4591 393 088
3 shiftsCOI522 5881 071 3061 647 4592 252 4202 887 629
OPEX57 416143 669258 692402 578575 560
BUDGET465 172927 6371 388 7671 849 8422 312 069

All amounts in PLN. COI is the cost of keeping the station staffed over a given horizon, OPEX is the running cost of the automated station (energy, service, residual attendance), BUDGET is the difference – the amount that can be put towards the investment.

Maximum net budget for automating one stationCOI minus the OPEX of a robotic station · by the assumed payback period
  • 1 shift
  • 2 shifts
  • 3 shifts
Maximum net budget for automating one station1 shift: 129, 258, 386, 514, 643. 2 shifts: 280, 559, 837, 1 114, 1 393. 3 shifts: 465, 928, 1 389, 1 850, 2 3120 k500 k1 000 k1 500 k2 000 k2 500 k12 mths · 1 shift: 129 k12912 mths · 2 shifts: 280 k28012 mths · 3 shifts: 465 k46512 mths24 mths · 1 shift: 258 k25824 mths · 2 shifts: 559 k55924 mths · 3 shifts: 928 k92824 mths36 mths · 1 shift: 386 k38636 mths · 2 shifts: 837 k83736 mths · 3 shifts: 1 389 k1 38936 mths48 mths · 1 shift: 514 k51448 mths · 2 shifts: 1 114 k1 11448 mths · 3 shifts: 1 850 k1 85048 mths60 mths · 1 shift: 643 k64360 mths · 2 shifts: 1 393 k1 39360 mths · 3 shifts: 2 312 k2 31260 mthsPLN net
Maximum net budget for automating one station1 shift: 129, 258, 386, 514, 643. 2 shifts: 280, 559, 837, 1 114, 1 393. 3 shifts: 465, 928, 1 389, 1 850, 2 3120 k1 000 k2 000 k3 000 kPLN net12 mths12928046524 mths25855992836 mths3868371 38948 mths5141 1141 85060 mths6431 3932 312
Maximum net budget for automating one station
12 mths24 mths36 mths48 mths60 mths
1 shift129258386514643
2 shifts2805598371 1141 393
3 shifts4659281 3891 8502 312

Why is 2020–2025 a turning point for industrial production in Poland?

It is hard not to notice how much the cost of living in Poland has risen in recent years – record inflation and rising loan instalments, fuel and food have affected all of us. That change also had consequences for employers, because average pay grew by 11.5% a year over that period — twice as fast as in the previous fifteen years. As a result, the budget that can now be put towards automation, assuming the same payback period, has risen by 70% in five years. COI – the cost of inaction – has risen by the same amount, and in the coming years it will be felt more and more, bearing directly on price pressure and competitiveness in the market – now also for the smaller companies which until now have approached production automation with a degree of reserve.

Average pay in Poland against the automation budgetaverage monthly pay in the national economy, GUS
  • 24-month budget for a 3-shift station
Average pay in Poland against the automation budgetaverage monthly pay in the national economy, GUS: 2 380, 3 225, 3 900, 5 167, 8 904. 24-month budget for a 3-shift station: 301, 401, 481, 630, 1 07102 0004 0006 0008 00010 0002005 · average monthly pay in the national economy, GUS: 2 380 PLN2 380 PLN20052010 · average monthly pay in the national economy, GUS: 3 225 PLN3 225 PLN20102015 · average monthly pay in the national economy, GUS: 3 900 PLN3 900 PLN20152020 · average monthly pay in the national economy, GUS: 5 167 PLN5 167 PLN20202025 · average monthly pay in the national economy, GUS: 8 904 PLN8 904 PLN20252005 · 24-month budget for a 3-shift station: 301 PLN301 k2010 · 24-month budget for a 3-shift station: 401 PLN401 k2015 · 24-month budget for a 3-shift station: 481 PLN481 k2020 · 24-month budget for a 3-shift station: 630 PLN630 k2025 · 24-month budget for a 3-shift station: 1 071 PLN1 071 kPLN gross / month
Average pay in Poland against the automation budgetaverage monthly pay in the national economy, GUS: 2 380, 3 225, 3 900, 5 167, 8 90405 00010 000PLN gross / month20052 380 PLN301 k20103 225 PLN401 k20153 900 PLN481 k20205 167 PLN630 k20258 904 PLN1 071 k
Average pay in Poland against the automation budget
20052010201520202025
average monthly pay in the national economy, GUS2 380 PLN3 225 PLN3 900 PLN5 167 PLN8 904 PLN
24-month budget for a 3-shift station301 PLN401 PLN481 PLN630 PLN1 071 PLN

Between 2005 and 2025 average pay rose by 274% — from 2 380.29 PLN to 8 903.56 PLN, an average of 6.8% a year GUS. That growth was, however, unevenly spread: 2005–2010 was 6.3% a year, 2010–2015 only 3.9%, 2015–2020 — 5.8%, and 2020–2025 as much as 11.5%. Over those five years pay rose by 3736 PLN gross, that is more than in the previous fifteen years put together.

That change overturns investment calculations made only a few years ago and points clearly to the only possible direction of development, leaving no room for debate about whether lower pay in Poland can go on driving economic growth. Only a higher degree of automation, better quality and higher throughput can do that.

When automation makes sense and when it is better to wait

Below are three real examples, calculated according to the model described in section 3.

CASE STUDY 1

Picking components for despatch

  • 1-shift operation
  • 3 operators work 8 h every day

Three people picked six different parts into a pouch, which was then heat-sealed and packed into a master carton by hand. The cycle time of one operator: 50 s per pouch, that is roughly one pouch every 16.7 s from three stations. After building an automatic component feeding station the cycle time is 10 s for a finished, sealed and packed pouch — a 67% increase in throughput.

Alternatively – a cheaper station with a 16 s cycle. Let us work out which pays off better if we are able to sell the surplus output.

Operator involvement fell to 10 minutes once every 4 hours.

  1. Station 1 – 16 s cycle, investment cost 340 thousand
  2. Station 2 – 10 s cycle, investment cost 420 thousand

Case study 1 — two station variants with the same staffing

Payback on the outlay
  • Station 1 · 16 s cycle · 340 thousand PLN
  • Station 2 · 10 s cycle · 420 thousand PLN
Payback on the outlayStation 1 · 16 s cycle · 340 thousand PLN: 0, 201,7, 403,4, 605,1, 806,8. Station 2 · 10 s cycle · 420 thousand PLN: 0, 200,5, 401, 601,5, 8020 k200 k400 k600 k800 k1 000 k061218240 · Station 1 · 16 s cycle · 340 thousand PLN: 0 k6 · Station 1 · 16 s cycle · 340 thousand PLN: 201,7 k12 · Station 1 · 16 s cycle · 340 thousand PLN: 403,4 k18 · Station 1 · 16 s cycle · 340 thousand PLN: 605,1 k24 · Station 1 · 16 s cycle · 340 thousand PLN: 806,8 k0 · Station 2 · 10 s cycle · 420 thousand PLN: 0 k6 · Station 2 · 10 s cycle · 420 thousand PLN: 200,5 k12 · Station 2 · 10 s cycle · 420 thousand PLN: 401 k18 · Station 2 · 10 s cycle · 420 thousand PLN: 601,5 k24 · Station 2 · 10 s cycle · 420 thousand PLN: 802 k10.1 mths12.5 mthscumulative net savingmonths from start-up
Payback on the outlayStation 1 · 16 s cycle · 340 thousand PLN: 0, 201,7, 403,4, 605,1, 806,8. Station 2 · 10 s cycle · 420 thousand PLN: 0, 200,5, 401, 601,5, 8020 k250 k500 k750 k1 000 k061218240 · Station 1 · 16 s cycle · 340 thousand PLN: 0 k6 · Station 1 · 16 s cycle · 340 thousand PLN: 201,7 k12 · Station 1 · 16 s cycle · 340 thousand PLN: 403,4 k18 · Station 1 · 16 s cycle · 340 thousand PLN: 605,1 k24 · Station 1 · 16 s cycle · 340 thousand PLN: 806,8 k0 · Station 2 · 10 s cycle · 420 thousand PLN: 0 k6 · Station 2 · 10 s cycle · 420 thousand PLN: 200,5 k12 · Station 2 · 10 s cycle · 420 thousand PLN: 401 k18 · Station 2 · 10 s cycle · 420 thousand PLN: 601,5 k24 · Station 2 · 10 s cycle · 420 thousand PLN: 802 k10.1 mths12.5 mthscumulative net savingmonths from start-up
Payback on the outlay
06121824
Station 1 · 16 s cycle · 340 thousand PLN0201,7403,4605,1806,8
Station 2 · 10 s cycle · 420 thousand PLN0200,5401601,5802
Annual production capacity
Annual production capacitypcs / year: 433, 452, 7230 k200 k400 k600 k800 kBy hand: 433 k pcs433 k pcsBy hand16.7 sStation 1: 452 k pcs452 k pcsStation 116 sStation 2: 723 k pcs723 k pcsStation 210 spcs / year (1 shift, 2 008 h)
Annual production capacitypcs / year: 433, 452, 7230 k250 k500 k750 kpcs / year (1 shift, 2 008 h)By hand16.7 s433 k pcsStation 116 s452 k pcsStation 210 s723 k pcs
Annual production capacity
By handStation 1Station 2
pcs / year433 k pcs452 k pcs723 k pcs
ITEMSTATION 1 (16 S)STATION 2 (10 S)
Investment cost340 000 PLN420 000 PLN
Staffing freed up (3 stations, 1 shift)439 150 PLN/year439 150 PLN/year
Net saving after OPEX403 423 PLN/year401 023 PLN/year
Payback period10.1 mths12.5 mths
Annual production capacity451 800 pcs722 880 pcs
Increase against manual work (16.7 s)+4.4%+67.0%
Capacity surplus over Station 1—+271 080 pcs/year

Station 1 pays back faster, because for the same freed-up staffing it costs 80 thousand PLN less. The difference, however, lies in throughput – Station 2 is able to produce 271 080 pcs more per year. For the comparison to account for different throughputs enabling additional sales, both variants have to be brought to the same throughput, and that means adding operators working by hand on a 50 s cycle to Station 1.

Cost: 1.875 × 146 383.21 PLN = 274 469 PLN a year
  1. One operator on a 50 s cycle: 2 008 h × 3 600 s / 50 s = 144 576 pcs/year
  2. Gap to close: 722 880 − 451 800 = 271 080 pcs/year
  3. Staffing needed: 271 080 / 144 576 = 1.875 staffed stations

At the same output of 722 880 pcs a year the account therefore looks like this:

DESCRIPTIONSTATION 1 + MANUAL STAFFINGSTATION 2
Outlay340 000 PLN420 000 PLN
Staffing freed up439 150 PLN/year439 150 PLN/year
OPEX: energy7 229 PLN/year7 229 PLN/year
OPEX: service (3% of the outlay)10 200 PLN/year12 600 PLN/year
OPEX total in each year17 429 PLN/year19 829 PLN/year
Additional manual staffing – year 1——
Additional manual staffing – year 2−288 192 PLN—
Additional manual staffing – year 3−302 602 PLN—
Net saving – year 1403 423 PLN401 023 PLN
Net saving – year 2136 274 PLN422 066 PLN
Net saving – year 3143 959 PLN444 160 PLN
ROI after 12 months+18.7%−4.5%
ROI after 24 months+58.7%+96.0%
ROI after 36 months+101.1%+201.7%

The cheaper station only wins in the first year, while sales stay at the same level. From the moment additional manual staffing appears, the advantage reverses for good: after 24 months Station 2's ROI is higher by 37 percentage points, and after 36 months by more than 100 points. Clearly – if there are no additional sales, Station 1 will ultimately generate the higher ROI thanks to its lower purchase price. It is worth being aware at the point of choosing a solution what a particular change can bring, so that you can ask yourself whether it is worth taking the risk today and paying more for a station with higher throughput. In the example given, increasing the investment by 80 thousand PLN could, over 3 years, bring an additional 583 593 PLN of savings compared with the cheaper solution – assuming that sales only grow in the second year after the solution goes live.

CASE STUDY 2

A collaborative robot applying protective elements

  • 3-shift operation
  • 2 operators work 8 h every day

Two operators were placing polystyrene protectors onto finished product leaving on a pallet. The size of the spacer forced two-person handling. The robot took over the placing operation, one person was moved to another station, and the second performs the remaining operations to prepare the despatch.

One station running three shifts is freed up, that is 522 588 PLN a year. Taking, by way of example, an outlay of 500 000 PLN, OPEX comes to 58 461 PLN a year: energy 21 686 PLN, service 15 000 PLN (3% of the outlay) and residual attendance 21 775 PLN. The net saving in the first year is 464 127 PLN, so the outlay pays back after 13 months.

Case study 2 — COI, OPEX and budgetstaffing freed up 522 588 PLN/year · outlay 500 000 PLN · values in thousand PLN
  • COI – the cost of inaction
  • OPEX of the automated station
  • BUDGET for the investment
Case study 2 — COI, OPEX and budgetCOI – the cost of inaction: 523, 1 071, 1 647, 2 252, 2 888. OPEX of the automated station: 58, 118, 179, 241, 304. BUDGET for the investment: 464, 953, 1 469, 2 012, 2 5840 k1 000 k2 000 k3 000 k12 mths · COI – the cost of inaction: 523 k52312 mths · OPEX of the automated station: 58 k5812 mths · BUDGET for the investment: 464 k46412 mths24 mths · COI – the cost of inaction: 1 071 k1 07124 mths · OPEX of the automated station: 118 k11824 mths · BUDGET for the investment: 953 k95324 mths36 mths · COI – the cost of inaction: 1 647 k1 64736 mths · OPEX of the automated station: 179 k17936 mths · BUDGET for the investment: 1 469 k1 46936 mths48 mths · COI – the cost of inaction: 2 252 k2 25248 mths · OPEX of the automated station: 241 k24148 mths · BUDGET for the investment: 2 012 k2 01248 mths60 mths · COI – the cost of inaction: 2 888 k2 88860 mths · OPEX of the automated station: 304 k30460 mths · BUDGET for the investment: 2 584 k2 58460 mthsPLN
Case study 2 — COI, OPEX and budgetCOI – the cost of inaction: 523, 1 071, 1 647, 2 252, 2 888. OPEX of the automated station: 58, 118, 179, 241, 304. BUDGET for the investment: 464, 953, 1 469, 2 012, 2 5840 k1 000 k2 000 k3 000 kPLN12 mths5235846424 mths1 07111895336 mths1 6471791 46948 mths2 2522412 01260 mths2 8883042 584

With an outlay of 500 000 PLN the budget after just 12 months (464 127 PLN) almost covers the investment, and after 24 months it generates an additional 453 thousand in savings.

Case study 2 — COI, OPEX and budget
12 mths24 mths36 mths48 mths60 mths
COI – the cost of inaction5231 0711 6472 2522 888
OPEX of the automated station58118179241304
BUDGET for the investment4649531 4692 0122 584
CASE STUDY 3

Running a test station + handover to the warehouse

  • 3-shift operation
  • 1 operator works 8 h every day
  • 2nd operator involved for 10 min once an hour

The operator loaded a component into the test machine, verifying 100% of production before despatch to the client. After the test they placed the part in a finished-product container. A second operator moved the containers to the warehouse on a trolley — that operation took 10 minutes once an hour. After automation a robot serves the test machine and places the parts into an automatic vertical store, which once full is collected by an AMR mobile robot and taken to the despatch warehouse.

One EOL station on three shifts is eliminated, plus 16% of the involvement in internal transport — together 606 thousand PLN a year. As you can see, without knowing the value of the investment you are already able to set your budget.

Case study 3 — COI, OPEX and budgetstaffing freed up 606 202 PLN/year · outlay not yet known · values in thousand PLN
  • COI – the cost of inaction
  • OPEX of the automated station
  • BUDGET for the investment
Case study 3 — COI, OPEX and budgetCOI – the cost of inaction: 606, 1 243, 1 911, 2 613, 3 350. OPEX of the automated station: 63, 160, 291, 455, 653. BUDGET for the investment: 543, 1 083, 1 621, 2 158, 2 6970 k1 000 k2 000 k3 000 k4 000 k12 mths · COI – the cost of inaction: 606 k60612 mths · OPEX of the automated station: 63 k6312 mths · BUDGET for the investment: 543 k54312 mths24 mths · COI – the cost of inaction: 1 243 k1 24324 mths · OPEX of the automated station: 160 k16024 mths · BUDGET for the investment: 1 083 k1 08324 mths36 mths · COI – the cost of inaction: 1 911 k1 91136 mths · OPEX of the automated station: 291 k29136 mths · BUDGET for the investment: 1 621 k1 62136 mths48 mths · COI – the cost of inaction: 2 613 k2 61348 mths · OPEX of the automated station: 455 k45548 mths · BUDGET for the investment: 2 158 k2 15848 mths60 mths · COI – the cost of inaction: 3 350 k3 35060 mths · OPEX of the automated station: 653 k65360 mths · BUDGET for the investment: 2 697 k2 69760 mthsPLN
Case study 3 — COI, OPEX and budgetCOI – the cost of inaction: 606, 1 243, 1 911, 2 613, 3 350. OPEX of the automated station: 63, 160, 291, 455, 653. BUDGET for the investment: 543, 1 083, 1 621, 2 158, 2 6970 k2 000 k4 000 kPLN12 mths6066354324 mths1 2431601 08336 mths1 9112911 62148 mths2 6134552 15860 mths3 3506532 697

The staffing freed up is 606 202 PLN a year, but the 12-month budget is 542 968 PLN – the difference of 63 234 PLN is taken by the OPEX of the automated station (energy 21 686 PLN, service 16 289 PLN, residual attendance 25 258 PLN).

Case study 3 — COI, OPEX and budget
12 mths24 mths36 mths48 mths60 mths
COI – the cost of inaction6061 2431 9112 6133 350
OPEX of the automated station63160291455653
BUDGET for the investment5431 0831 6212 1582 697

When it is better to wait or look at a different process

  1. The saving exists only on paper. The model works only when the staffing cost actually disappears: the person moves to another station, you do not start another shift, or you do not hire additional people as orders grow.
  2. The process is not repeatable. If the dimensional tolerances of the components are wide and success depends on what the operator compensates for with experience and a practised hand, automation can be expensive and hard to implement.
  3. One workstation, one shift. At a median of 7 690.82 PLN the 24-month budget for one staffed station is 258 thousand PLN. Most stations that deliver the autonomy which generates the largest savings cost more, so such a project has to be calculated over 36–60 months.
  4. A short time horizon with no possibility of reuse. If production of a particular product is ending soon and the station is a dedicated one, continuing to use it may prove impossible and modifying it uneconomic. In that case robotic stations have the advantage that they are easier to adapt to a new product or an entirely different process.
  5. Small batches, high production variability. If production consists of small batches forcing frequent changeovers, changes to tool geometry or the swapping of assemblies, operator involvement may stay high, which will significantly reduce the budget and lengthen the payback period.

FAQ

Does giving the supplier a budget mean I will get the most expensive quote?
This is the biggest myth — prices are set by the market. If the supplier's calculation comes to 300 thousand PLN, being told the budget is 500 thousand will not change that figure. What it will change is the subject of the conversation: from price to scope — whether throughput can be increased, whether the station can be adapted to produce a different part, whether functionality that was not considered can be added.
What is the difference between SSF and SCF?
SSF (Shift Staffing Factor) says how many people have to be employed for a station to be staffed at all times — it follows from holidays, sick leave, training and medical check-ups. SCF (Shift Cost Factor) says how much more expensive the same worker is in a multi-shift system — it follows from night-work and shift allowances and from higher absence and turnover.
What payback period is realistic?
On 3-shift operation, depending on how complex the station is and how much operator involvement is needed, 12–24 months is realistic. With a single station on a single shift the payback period will be correspondingly longer.
I have no maintenance department — who will fix a breakdown?
The station can be supplied with an industrial router for remote diagnostics — an engineer connects to the machine within hours, not days, which makes it possible to solve the problem or decide on the next steps.
Where do I start if I do not know which process to automate?
Start by identifying the places that tie up the largest number of operators, preferably with long production runs that do not require constant changes or changeovers. To begin with, look for simple processes: packing, palletising, the assembly of a few components. If you do not know how to go about it and need help, get in touch with us.
Photo:  Szymon Wasiński

About the author

Szymon Wasiński

Founder and co-owner of ATIV

He has worked in production automation for 12 years. He started out in automotive, in lean management and assembly process analysis. As an engineer he was responsible for machine specifications, FAT and SAT acceptance tests and vision inspection systems. He has visited dozens of plants and is still struck by how differently each one solves the same processes.

At ATIV he is responsible for strategy, running projects and advising on return on investment. A team of around 10 engineers runs projects from concept, through FAT, to SAT and operator training — with no stage subcontracted.

LinkedIn profile